NATIONAL INSURANCE PROPERTY DEVELOPMENT COMPANY LIMITED
Annual Schedule of Planned Procurement Activities
No. | Project Number | Project Name | UNSPSC Code Lvl 3 | Brief Description | Proposed date for Issuing of Bidding Documents | Expected Delivery/Completion Date (of Procurement) | Expected Delivery/Completion Date (of Project - exclu DNP) | Estimated Project Duration (for works and services) | Procurement Method | Standstill Period (if applicable) - No. of days | Contract Type | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Flood Mitigation and Erosion Control Programme | ||||||||||||||||||||||
1 | MOWT-DHO-NIPDEC-08/14/42 | Construction of a Reinforced Concrete Wall along the San Juan River, Saddle Road, Lower Santa Cruz | Construction of a Reinforced Concrete Wall along the San Juan River, Saddle Road, Lower Santa Cruz | Nov-23 | Jan-24 | May-24 | 4 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
2 | MOWT-DHO-NIPDEC-08/14/47 | Construction of a Reinforced Concrete Wall along Cunapo River, Eastern Main Road, Sangre Grande | Construction of a Reinforced Concrete Wall along Cunapo River, Eastern Main Road, Sangre Grande | Nov-23 | Jan-24 | May-24 | 4 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
3 | MOWT-DHO-NIPDEC-08/14/43 | Construction of a Reinforced Concrete Wall along Aripo River, LP#58, Carib Circular, La Platta Gardens | Construction of a Reinforced Concrete Wall along Aripo River, LP#58, Carib Circular, La Platta Gardens | Nov-23 | Jan-24 | May-24 | 4 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
4 | MOWT-DHO-NIPDEC-08/14/44 | Construction of a Reinforced Concrete Wall along Petit Valley Ravine, D/S Morne Coco Road, Petit Valley | Construction of a Reinforced Concrete Wall along Petit Valley Ravine, D/S Morne Coco Road, Petit Valley | Nov-23 | Jan-24 | May-24 | 4 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
5 | DD-NIPDEC-08/14/45 | Construction of Reinforced Concrete Wall along Mausica River in the Vicinity of the Basketball Court on Mendez Trace, Arima | Construction of Reinforced Concrete Wall along Mausica River in the Vicinity of the Basketball Court on Mendez Trace, Arima | Nov-23 | Jan-24 | May-24 | 4 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
6 | DD-NIPDEC-08/14/48 | Rehabilitation Works along the Arima River Downstream of the Churchill Roosevelt Highway | Rehabilitation Works along the Arima River Downstream of the Churchill Roosevelt Highway | Dec-23 | Feb-24 | Jun-24 | 4 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
7 | DD-NIPDEC-08/14/49 | Construction of a Reinforced Concrete Wall Along Esmeralda Main Drain, Johnathan Trace, Cunupia | Construction of a Reinforced Concrete Wall Along Esmeralda Main Drain, Johnathan Trace, Cunupia | Dec-23 | Feb-24 | Jun-24 | 4 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
8 | DD-NIPDEC-08/14/50 | Construction of a Reinforced Concrete Wall Along Fernando Lane Outfall Drain, LP #6 Fernando Lane, Esmeralda Road, Cunupia | Construction of a Reinforced Concrete Wall Along Fernando Lane Outfall Drain, LP #6 Fernando Lane, Esmeralda Road, Cunupia | Dec-23 | Feb-24 | Jun-24 | 4 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
9 | DD-NIPDEC-08/14/51 | Construction of a Reinforced Concrete U-Section along Lallan River, from Egypt Trace to Jerningham Railway Road, Endeavour | Construction of a Reinforced Concrete U-Section along Lallan River, from Egypt Trace to Jerningham Railway Road, Endeavour | Dec-23 | Feb-24 | Jun-24 | 4 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
10 | DD-NIPDEC-08/14/52 | Construction of a Reinforced Concrete Wall along La Cuesa River, Alongside Northbound Ramp, Freeport Overpass | Construction of a Reinforced Concrete Wall along La Cuesa River, Alongside Northbound Ramp, Freeport Overpass | Dec-23 | Feb-24 | Jun-24 | 4 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
11 | DD-NIPDEC-08/14/53 | Rehabilitation & Desilting Works Along Cipero River Mouth | Rehabilitation & Desilting Works Along Cipero River Mouth | Jan-24 | Mar-24 | Jul-24 | 4 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
12 | DD-NIPDEC-08/14/54 | Construction of Reinforced Concrete Walls along Vistabella River | Construction of Reinforced Concrete Walls along Vistabella River | Jan-24 | Mar-24 | Jul-24 | 4 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
13 | DD-NIPDEC-08/14/55 | Construction of Reinforced Concrete Retaining Wall on Nagessar Channel | Construction of Reinforced Concrete Retaining Wall on Nagessar Channel | Jan-24 | Mar-24 | Jul-24 | 4 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
No. | Project Number | Project Name | UNSPSC Code Lvl 3 | Brief Description | Proposed date for Issuing of Bidding Documents | Expected Delivery/Completion Date (of Procurement) | Expected Delivery/Completion Date (of Project - exclu DNP) | Estimated Project Duration (for works and services) | Procurement Method | Standstill Period (if applicable) - No. of days | Contract Type | |||||||||||
Flood Mitigation and Erosion Control Programme | ||||||||||||||||||||||
14 | DD-NIPDEC-08/14/56 | Construction of a Reinforced Concrete Wall along Guaracara River, Guaracara Tabaquite Road., Williamsville | Construction of a Reinforced Concrete Wall along Guaracara River, Guaracara Tabaquite Road., Williamsville | Jan-24 | Mar-24 | Jul-24 | 4 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
Bridges Reconstruction Programme (Phase 3B) | ||||||||||||||||||||||
15 | CP53 | Design and Supervision of B1/71 Paria Main Road | Design and Supervision of B1/71 Paria Main Road | Jan-24 | Mar-24 | Apr-26 | 24 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
16 | CP54 | Design and Supervision of B2/12 Cumuto Road | Design and Supervision of B2/12 Cumuto Road | Jan-24 | Mar-24 | Apr-26 | 24 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
17 | CP55 | Design and Supervision of B1/1 Clair Street Extension, Edinburgh 500 | Design and Supervision of B1/1 Clair Street Extension, Edinburgh 500 | Jan-24 | Mar-24 | Apr-26 | 24 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
18 | CP56 | Design and Supervision of B2/3 Plum Mitan Road | Design and Supervision of B2/3 Plum Mitan Road | Jan-24 | Mar-24 | Apr-26 | 24 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
19 | CP57 | Design and Supervision of B1/14 Plum Mitan Road | Design and Supervision of B1/14 Plum Mitan Road | Jan-24 | Mar-24 | Apr-26 | 24 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
20 | CP58 | Design and Supervision of B1/18 Mayaro/Guayaguayare | Design and Supervision of B1/18 Mayaro/Guayaguayare | Jan-24 | Mar-24 | Apr-26 | 24 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
21 | CP59 | Design and Supervision of B1/1 Piparo Road | Design and Supervision of B1/1 Piparo Road | Jan-24 | Mar-24 | Apr-26 | 24 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
22 | CP60 | Design and Supervision of B1/1 Garth Road | Design and Supervision of B1/1 Garth Road | Jan-24 | Mar-24 | Apr-26 | 24 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
23 | CP61 | Design and Supervision of B2/1 Cipero Road | Design and Supervision of B2/1 Cipero Road | Jan-24 | Mar-24 | Apr-26 | 24 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
24 | CP62 | Design and Supervision of B2/11 Cipero Road | Design and Supervision of B2/11 Cipero Road | Jan-24 | Mar-24 | Apr-26 | 24 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
25 | CP63 | Design and Supervision of B1/15 SS Erin Road | Design and Supervision of B1/15 SS Erin Road | Jan-24 | Mar-24 | Apr-26 | 24 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
26 | CP64 | Design and Supervision of B1/791 Southern Main Road | Design and Supervision of B1/791 Southern Main Road | Jan-24 | Mar-24 | Apr-26 | 24 months | Open Bidding | 10 | Fixed term contract | ||||||||||||
Caribbean Telecommunication Union Headquarters | ||||||||||||||||||||||
27 | CTU-001 | Design Services for Refurbishment and Outfitting of Caribbean Telecommunications Union Headquarters | Design Services for Refurbishment and Outfitting of Caribbean Telecommunications Union Headquarters | Apr-24 | Jun-24 | Nov-24 | 3 months | Selective Bidding | 10 | Fixed term contract | ||||||||||||
28 | NA | Internal Audit Training | Annual training for Manager and three (3) employees | Jun-24 | Request for Quotation | Purchase Order | ||||||||||||||||
29 | NA | Internal Audit PPE | Purchase of one (1) pair of boots and two (2) helmets | Mar-24 | Request for Quotation | Purchase Order | ||||||||||||||||
30 | NA | Internal Audit Week | Celebrtion of International Internal Audit Month | Mar-24 | Request for Quotation | Purchase Order | ||||||||||||||||
31 | NA | Painting of Internal Audit Offices | Maintenance of department | Jun-24 | Request for Quotation | Purchase Order | ||||||||||||||||
32 | NA | Internal Audit Miscellaneous Expenses | Purchase of books, stationery, computer equipment etc. | Jun-24 | Request for Quotation | Purchase Order | ||||||||||||||||
33 | NA | Office of the DPP administration building | Bridge financing for construction and mortgage financing | Mar-24 | Mar-26 | 24 months | Selective Competitive Tender | 10 | Fixed term contract | |||||||||||||
PURE UNIT | ||||||||||||||||||||||
34 | NA | Almond Drive [Drainage & Road Works] Off De Norbriga, Morvant | Road Rehabilitation Works | Oct-23 | Dec-23 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
35 | NA | Aranguez Main Road [Road Works] From Delta Glass to Np Gas Station | Road Rehabilitation Works | May-23 | Jun-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
36 | NA | Arena Road [Concrete, Drainage & Road Works] Brazil | Road Rehabilitation Works | Oct-23 | Dec-23 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
37 | NA | Balata Hill Road [Slope Stabilization & Associated Works] 0km - 2.8km | Slope Stabilization Works | Jun-24 | Aug-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
38 | NA | Barataria Ramp and Underpass Upgrade Barataria | Traffic Management Measure | Apr-24 | Jul-24 | 90 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
39 | NA | Biche Ortoire [Slope Stabilization & Associated Works] 0.0 - 1.0 km | Slope Stabilization Works | Apr-24 | Jun-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
40 | NA | Biljah Road [Road Rehabilitation] Off Caroni Savannah Road | Road Rehabilitation Works | Nov-23 | Dec-23 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
41 | NA | Blanchisseuse Road [Concrete Works - Package 13] Ch 3+000 to 4+500 | Road Rehabilitation Works | May-24 | Jul-24 | 30 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
42 | NA | Blanchisseuse Road [Roadworks - Package 12] Ch 1+500 to 3+000 | Road Rehabilitation Works | Apr-24 | Jun-24 | 30 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
43 | NA | Bon Air Road [Slope Stabilization & Associated Works] 0-3.2km | Slope Stabilization Works | Jan-24 | Mar-24 | 30 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
44 | NA | Bosierre Trace (Bridge Reconstruction) Off Gran Couva Main Road | Bridge Works | Feb-24 | Aug-24 | 181 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
45 | NA | Bowen Street [Road Rehabilitation] From Eastman Street to Sapodilla Street, Tunapuna | Road Rehabilitation Works | Nov-23 | Nov-23 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
46 | NA | Buen Intento Road [Roadworks] 1.0km - 3.5km Goupal Rd | Road Rehabilitation Works | Jun-24 | Jul-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
47 | NA | Cantaro Extension [Road Rehabilitation] From Saddle Road to Maraj Trace | Road Rehabilitation Works | Nov-23 | Dec-23 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
48 | NA | Cap de Ville to Erin [RR - Package 4] To Be Determined | Road Rehabilitation Works | Aug-24 | Sep-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
49 | NA | Caparo Brasso Valley Road [Road Rehabilitation] - Phase 2 Depot Road to Ravine Sable Road | Road Rehabilitation Works | Dec-23 | Jan-24 | 15 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
50 | NA | Caparo Brasso Valley Road [Road Rehabilitation] - Phase 3 From KFC to Depot Road | Road Rehabilitation Works | Jan-24 | Feb-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
51 | NA | Carli Bay Road [Road Works] 0km - 2km Chins Supermarket to Carli Bay Fishing Facility | Road Rehabilitation Works | Jun-24 | Jul-24 | 15 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
52 | NA | Cayman Avenue [Road Rehabilitation] Off River Estate Circular, Diego Martin | Road Rehabilitation Works | Nov-23 | Nov-23 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
53 | NA | Cedar Hill Road (Patching Works) | Road Rehabilitation Works | Feb-24 | Mar-24 | 5 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
54 | NA | Chickland Caparo Road [Road Works] 0km - 2km Arena Road to Caparo Valley Brasso Road | Road Rehabilitation Works | Jul-24 | Aug-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
55 | NA | Church Hill Extension [Road Rehabilitation] Off Bushe Street, San Juan | Road Rehabilitation Works | Nov-23 | Jan-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
56 | NA | Churchill Roosevelt Highway - Construction of 3rd Lane - Eastbound From Andrew Lane to O'Meara Road | Traffic Management Measure | Nov-23 | Jul-24 | 240 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
57 | NA | Cipero Road [Slope Stabilization & Associated Works] 1km - 12km Retrench (connector Junction) to Health centre | Slope Stabilization Works | May-24 | Jul-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
58 | NA | Cunapo Southern Road [Road Rehabilitation - Patching] Plum Mitan Road to Tabaquite Road | Road Rehabilitation Works | Jun-24 | Aug-24 | 30 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
59 | NA | Cunapo Southern/ Charuma Junction Road [Slope Stabilization] 12km length Cushe to Tabaquite Rio | Slope Stabilization Works | Jun-24 | Aug-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
60 | NA | Dove Lane [Road Rehabilitation] Off River Estate Circular, Diego Martin | Road Rehabilitation Works | Nov-23 | Jan-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
61 | NA | El Socorro Road [Road Works] From Aranguez-El Socorro Access Road to Railway Road | Road Rehabilitation Works | May-24 | Jun-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
62 | NA | Finch Drive [Road Rehabilitation] Off River Estate Circular, Diego Martin | Road Rehabilitation Works | Oct-23 | Jan-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
63 | NA | First Street Extension [Drainage & Road Works] Off First Street, Mt Lambert | Road Rehabilitation Works | Nov-23 | Jan-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
64 | NA | Fisher & Moore Avenue [Road Rehabilitation] Off St. Ann's Road | Road Rehabilitation Works | Nov-23 | Dec-23 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
65 | NA | Flamingo Avenue [Road Rehabilitation Off River Estate Circular, Diego Martin | Road Rehabilitation Works | Oct-23 | Jan-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
66 | NA | Garth Road (Bridge Reconstruction) Scale Road Junction | Bridge Works | Mar-24 | Sep-24 | 180 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
67 | NA | Garth Road [Roadworks] 1.5km - 3.5km Brothers Road Presbterian school to Radicas Roti Shop | Road Rehabilitation Works | Jan-24 | Feb-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
68 | NA | Golden Grove Road [Road Works] Off Eastern Main Road, Arouca | Road Rehabilitation Works | Jun-24 | Jul-24 | 15 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
69 | NA | Gran Couva Main Road [Roadworks - Package 2] 13km length From Highway to Caparo Valley Road | Road Rehabilitation Works | Mar-24 | May-24 | 30 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
70 | NA | Grand Curacaye Road [Concrete, Drainage & Road Works] Off Saddle Road, Santa Cruz | Road Rehabilitation Works | Nov-23 | Feb-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
71 | NA | Granville Road [Slope Stabilization] 0km - 4.5km From SMR 106.225 to Granville Beach | Slope Stabilization Works | Apr-24 | Jun-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
72 | NA | Grasshopper Lane [Road Rehabilitation] Off River Estate Circular, Diego Martin | Road Rehabilitation Works | Oct-23 | Jan-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
73 | NA | Guapo Cap-de-Ville Road [Roadworks] 0km - 4km From Chunilal Trace | Road Rehabilitation Works | Mar-24 | Apr-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
74 | NA | Heights of Guanapo [Slope Stabilization] 0-12km | Slope Stabilization Works | May-24 | Jul-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
75 | NA | Hermitage Road [Roadworks] 0.0km to 4.8km From KFC St Margrets Junction to Macaulay Flyover | Road Rehabilitation Works | Apr-24 | May-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
76 | NA | Hermitage Road Union Village (Bridge Reconstruction) Claxton Bay, near Union Presbyterian School | Bridge Works | Feb-24 | Aug-24 | 180 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
77 | NA | Hillcrest View [Drainage & Road Works] Off La Canoa Road, Saddle Road, Santa Cruz | Road Rehabilitation Works | Oct-23 | Dec-23 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
78 | NA | Hillview Road [Drainage & Road Works] Off 6th Avenue, Malick | Road Rehabilitation Works | Jul-23 | Feb-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
79 | NA | Hirondelle Street [Drainage & Road Works] Off Lady Young Road, Morvant | Road Rehabilitation Works | Jul-23 | Apr-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
80 | NA | Hutchinson Drive [Road Works] La Romaine | Road Rehabilitation Works | Jul-23 | Jan-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
81 | NA | Ibis Drive [Road Rehabilitation] Off River Estate Circular, Diego Martin | Road Rehabilitation Works | Jul-23 | Jan-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
82 | NA | Improvement to Endeavour Interchange - Phase 2 (Chaguanas Traffic Alleviation) In the vicinity of Mulchan Seuchan Road | Traffic Management Measure | Feb-24 | Aug-24 | 180 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
83 | NA | Jackson Street & Hislop Street [Drainage & Road Works] Off Eastern Main Road & Off Real Street | Road Rehabilitation Works | Aug-23 | Mar-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
84 | NA | KP Lands - La Platta Gardens [Road Rehabilitation] Off Eastern Main Road, Valencia | Road Rehabilitation Works | Jun-23 | Feb-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
85 | NA | La Seiva Road [Road Rehabilitation] From Toco Main Road to Foster Road | Road Rehabilitation Works | Jun-23 | Mar-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
86 | NA | Laventille Extension Road [Road Rehabilitation] From St. Francois Valley Road to Mon Repos | Road Rehabilitation Works | Jul-23 | Mar-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
87 | NA | Lemon Drive [Road Works] Off Mendez Drive, Champ Fleurs | Road Rehabilitation Works | Aug-23 | Jan-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
88 | NA | Lopinot Road [Road Rehabilitation] From Dunderhill to Xandu Resort | Road Rehabilitation Works | Aug-23 | Feb-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
89 | NA | Lopinot Road [Road Works - Package 2] 0-13km | Road Rehabilitation Works | Jun-24 | Jul-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
90 | NA | Lopinot Road [Slope Stabilization - Package 1] LP 26 | Slope Stabilization Works | May-24 | Aug-24 | 75 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
91 | NA | Lopinot Road [Slope Stabilization - Package 2] LP 29 | Slope Stabilization Works | May-24 | Aug-24 | 75 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
92 | NA | LP# 154 to LP# 157 Lopinot Road [Road Works] La Pastora | Road Rehabilitation Works | Aug-23 | Feb-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
93 | NA | LP# 159 San Francisco Road [Road Works] La Pastora | Road Rehabilitation Works | Aug-23 | Feb-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
94 | NA | LP# 180 to LP# 172 Lopinot Road [Drainage & Road Works] La Pastora | Road Rehabilitation Works | Aug-23 | May-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
95 | NA | LP# 68 Mayo Rd [Slope Stabilization & Associated Works] Mayo Road | Slope Stabilization Works | Jul-23 | Jun-24 | 90 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
96 | NA | LP162 to LP168 San Francisco Road [Road Rehabilitation] La Pastora | Road Rehabilitation Works | Aug-23 | Feb-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
97 | NA | M2 Ring Road [Slope Stabilization] 8.0 km to 15.39 km Picton Road Junction to Manahambre Road Junction | Slope Stabilization Works | Jun-24 | Sep-24 | 75 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
98 | NA | Mahogany Drive [Road Works] Off Samaan Drive, Olton Road | Road Rehabilitation Works | Jun-23 | Jan-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
99 | NA | Maingot Road [Road Rehabilitation] Off Tunapuna Road | Road Rehabilitation Works | Jul-23 | Dec-23 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
100 | NA | Manahambre Road [Road Rehabilitation] - Phase 3 TBD | Road Rehabilitation Works | Feb-24 | Mar-24 | 15 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
101 | NA | Maraval Access Road Upgrade [Bridge Reconstruction & Associated Works] Saddle Road, Maraval | Road Rehabilitation Works | Jul-23 | Jun-24 | 180 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
102 | NA | Matilda Road [Roadworks] From Matilda Junction to Moruga Rd | Road Rehabilitation Works | Jul-24 | Aug-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
103 | NA | Mausica Road South [Roadworks] From CRH to Carapo Road | Road Rehabilitation Works | Jan-24 | Feb-24 | 15 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
104 | NA | Mayaro Guayaguayare Road [Slope Stabilization] 9.5km-21km | Slope Stabilization Works | Jan-24 | Apr-24 | 75 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
105 | NA | Mayo Road [Roadworks] 0km - 4.6km Juction of Couva Road to Junction of Cedar Hill Road | Road Rehabilitation Works | Jun-24 | Aug-24 | 30 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
106 | NA | Mc Carthy Street [Road Rehabilitation] Off Cantaro Extension, Saddle Road, Santa Cruz | Road Rehabilitation Works | Jun-23 | Feb-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
107 | NA | Morne Coco Road Slope Stabilization Pk2 Off Morne Coco Off Pionaire Drive | Slope Stabilization Works | Feb-24 | May-24 | 59 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
108 | NA | Naggee Road [Slope Stabilization] 1.85km -4.3km Opposite Lp# 42 | Slope Stabilization Works | Jul-24 | Sep-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
109 | NA | North Coast Road [Drainage Works] From Pillars to Maracas Bay | Road Rehabilitation Works | Jun-23 | Apr-24 | 45 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
110 | NA | North Coast Road [Road Rehabilitation] From La Fillette to Blanchisseuse | Road Rehabilitation Works | Jun-23 | Jan-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
111 | NA | North Coast Road [Road Works - Phase 1] From Pillars, Chainage 0+000 to 4+900 | Road Rehabilitation Works | Jun-23 | Jan-24 | 30 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
112 | NA | North Coast Road [Road Works - Phase 2] From Chainage 4+900 to 7+400 | Road Rehabilitation Works | Jun-23 | Jan-24 | 30 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
113 | NA | North Coast Road [Road Works - Phase 3] From Chainage 7+550 to 12+850 | Road Rehabilitation Works | Jun-23 | Jan-24 | 30 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
114 | NA | North Manzanilla Road [Slope Stabilization] 0-5km | Slope Stabilization Works | Jun-24 | Aug-24 | 30 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
115 | NA | Oasis Gardens [Drainage Works] Off Northpost Road | Road Rehabilitation Works | Jun-23 | Feb-24 | 45 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
116 | NA | Ojoe Road [Road Rehabilitation] Off Brierley Street, Sangre Grande | Road Rehabilitation Works | Jul-23 | Jan-24 | 15 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
117 | NA | Oliver Trace Extension [Road Works] Off William Street, Mt D'or | Road Rehabilitation Works | Aug-23 | Feb-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
118 | NA | O'Meara Road North [Road Rehabilitation] Between O'Conner Street and PBR | Road Rehabilitation Works | Mar-24 | Apr-24 | 15 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
119 | NA | Parakeet Avenue [Road Rehabilitation] Off River Estate Circular, Diego Martin | Road Rehabilitation Works | Jul-23 | Jan-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
120 | NA | Paria Main Road [Slope Stabilization - Package 1] 0km - 6km, 25km-30km | Slope Stabilization Works | Feb-24 | May-24 | 90 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
121 | NA | Paria Main Road [Slope Stabilization - Package 2] 69.3 km mark | Slope Stabilization Works | Jun-24 | Aug-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
122 | NA | Paria Morne Bleu Road [Slope Stabilization] 0-6.4km | Slope Stabilization Works | Jan-24 | Mar-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
123 | NA | Park Street [Road Rehabilitation], Laventille Off Ariapita Avenue, Port of Spain | Road Rehabilitation Works | Aug-23 | Dec-23 | 5 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
124 | NA | Park Street [Road Rehabilitation], POS Off Lady Young Road, Morvant | Road Rehabilitation Works | Jul-23 | Feb-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
125 | NA | Penal Rock Road [Roadworks] 20km-25km | Slope Stabilization Works | Feb-24 | Mar-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
126 | NA | Penal Rock Road [Slope Stabilization] Lp# 493 23.1km mark | Road Rehabilitation Works | Feb-24 | Apr-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
127 | NA | Plum Mitan Road [Road Rehabilitation - Patching] From Manzanilla Mayaro Road to Cunapo Southern Main Road | Road Rehabilitation Works | Feb-24 | Apr-24 | 30 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
128 | NA | Point Fortin Road [Roadworks] 0km - 4km From Dunlop Roundabout to Atlantic LNG | Road Rehabilitation Works | Jun-24 | Jul-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
129 | NA | Ponta Rosa Drive & Good Will Drive [Road Rehabilitation] Off Bushe Street, Opposite Julie Field Road | Road Rehabilitation Works | Aug-23 | Nov-23 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
130 | NA | Primus Street & Delaney Trace [Road Rehabilitation] Off Toco Main Road, Salybia | Road Rehabilitation Works | Aug-23 | Jan-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
131 | NA | Ragoo Street [Road Rehabilitation] Off Meade Street | Road Rehabilitation Works | Jul-23 | Feb-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
132 | NA | Rainbow Ridge [Road Works], Off Terracevale Road, Goodwood Avenue, Goodwood Park | Road Rehabilitation Works | Jan-24 | Feb-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
133 | NA | Roads 1-5 North Eastern Settlement [Road Rehabilitation] Off Ojoe Road, Sangre Grande | Road Rehabilitation Works | Jun-23 | Nov-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
134 | NA | Rupert Trace (Roadworks) Off Bellevue St James | Road Rehabilitation Works | Jan-24 | Feb-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
135 | NA | Saddle Road [Roadworks] Febeau Village to Petit Boug | Road Rehabilitation Works | Jan-24 | Feb-24 | 15 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
136 | NA | Samuel Cooper [Slope Stabilization] 1.65km Near to area known as the "Dump" | Slope Stabilization Works | May-24 | Jul-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
137 | NA | Sangre Grande to Manzanilla [Road Rehabilitation, Road Widening & Culvert Reconstruction - Package 4] Chainage 6+000 to 8+000 | Traffic Management Measure | Oct-23 | Sep-24 | 300 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
138 | NA | Sangre Grande to Manzanilla [Road Rehabilitation, Road Widening & Culvert Reconstruction - Package 5] Chainage 8+000 to 10+000 | Traffic Management Measure | Oct-23 | Sep-24 | 300 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
139 | NA | Second Trace [Road Rehabilitation] Off Bagatelle Main Road, Diego Martin | Road Rehabilitation Works | Aug-23 | Feb-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
140 | NA | Sellier Street [Road Rehabilitation] From Frederick Street, Curepe | Road Rehabilitation Works | Jun-23 | Nov-23 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
141 | NA | Siparia Road [Slope Stabilization] 0km - 11.782km From Oropouche Roundabout to Siparia Road Junction | Slope Stabilization Works | Jun-24 | Sep-24 | 90 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
142 | NA | Sir Solomon Hochoy Highway [Construction of Additional Lanes North & South from Chaguanas to Chase Village - Package 1] From Chainage 0+000 to 1+400 | Traffic Management Measure | Aug-23 | Sep-24 | 365 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
143 | NA | Sir Solomon Hochoy Highway [Construction of Additional Lanes North & South from Chaguanas to Chase Village - Package 2] From Chainage 1+400 to 3+400 | Traffic Management Measure | Aug-23 | Sep-24 | 365 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
144 | NA | Sisters Road [Roadworks] 3.5km-6.2km | Road Rehabilitation Works | Aug-24 | Sep-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
145 | NA | Smart Street [Road Rehabilitation] From Warren Street to Fraser Street | Road Rehabilitation Works | Jun-23 | May-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
146 | NA | Southern Main Road (Concrete Works) Pkg 2 Claxton Bay (Superfoods to TCL) | Road Rehabilitation Works | May-24 | Jul-24 | 45 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
147 | NA | Southern Main Road [Road Rehabilitation] From Alice Street to Church Street, La Romaine | Road Rehabilitation Works | Jul-23 | Feb-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
148 | NA | Southern Main Road [Road Works] 26km - 28km St Marys Junction to Beaucarro Road | Road Rehabilitation Works | May-24 | Jun-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
149 | NA | Southern Main Road 8km Savonetta to Petrotrin | Road Rehabilitation Works | Nov-23 | Dec-23 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
150 | NA | Southern Main Road Upgrade From HDC Development to Farm Road | Traffic Management Measure | May-24 | Aug-24 | 90 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
151 | NA | Southern Main Road, Cedros to Icacos [Road Rehabilitation - Package 2] | Road Rehabilitation Works | Aug-24 | Sep-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
152 | NA | Southern Main Road/ San Fernando Bye Pass [Roadworks] 3km Tarouba Roundabout to Point a Pierre Roundabout (gas station) | Road Rehabilitation Works | Feb-24 | Mar-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
153 | NA | SS Erin Road [Roadworks] 1Km to 5.5 Km Bennet Drive to Dumfries Road Junction | Road Rehabilitation Works | Mar-24 | Apr-24 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
154 | NA | SS Erin Road [Slope Stabilization] 18km Cotton Trace to Los Iros Junction | Slope Stabilization Works | Apr-24 | Jun-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
155 | NA | St Julien Road (Slope Stabilization 1) St Julien Road, LP #83 | Slope Stabilization Works | Mar-24 | May-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
156 | NA | Talparo Mundo Nuevo Road [Slope Stabilization] 0-9km | Slope Stabilization Works | Mar-24 | May-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
157 | NA | Thunderbird Lane [Road Rehabilitation] Off River Estate Circular, Diego Martin | Road Rehabilitation Works | Jul-23 | Jan-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
158 | NA | Tomato Trace [Road Works] Off Northpost Road, Diego Martin | Road Rehabilitation Works | Aug-23 | Feb-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
159 | NA | Torrib Tabaquite Road [Slope Stabilization - Package 1] 0km-10km | Slope Stabilization Works | Apr-24 | Jun-24 | 60 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
160 | NA | Toucan Drive [Road Rehabilitation] Off River Estate Circular, Diego Martin | Road Rehabilitation Works | Jul-23 | Jan-24 | 10 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
161 | NA | Tumpuna Road (North) [Road Rehabilitation] | Road Rehabilitation Works | Nov-23 | Jan-24 | 30 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
162 | NA | Tumpuna Road Upgrade Arima | Traffic Management Measure | Oct-23 | Sep-24 | 330 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
163 | NA | Tunapuna Road [Road Rehabilitation] From Hendrickson Street to end of Tunapuna Road | Road Rehabilitation Works | Jul-23 | Nov-23 | 20 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
164 | NA | Upper Sea View Hill [Concrete Drainage, Road Works & Slope Stabilization] Off Abbe Pouja Road, Carenage | Slope Stabilization Works | Jun-24 | Sep-24 | 90 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
165 | NA | Uriah Butler Highway - Northbound [Road Rehabilitation] Between Chaguanas and Grand Bazaar | Road Rehabilitation Works | Jun-23 | Feb-24 | 30 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
166 | NA | Uriah Butler Highway - Southbound [Road Rehabilitation] Between Grand Bazaar and Chaguanas | Road Rehabilitation Works | Jun-23 | Feb-24 | 30 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
167 | NA | Waterloo Road [Road Works] 6.5km - 8.5km Waterloo Cremation Site to Orange Valley Bay Road | Road Rehabilitation Works | Aug-24 | Sep-24 | 15 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
168 | NA | Yaigual Road [Slope Stabilization] 0-2.4km | Slope Stabilization Works | Jul-24 | Sep-24 | 30 days | Selective Tendering/Limited Tendering | 10 | Unit Price | |||||||||||||
169 | NA | NIPDEC Rebrand | Company wide brand rejuvination, new logo, colours, signage, website, social media, etc. | Mar-24 | May-24 | Open Tender | 10 | |||||||||||||||
CENTRAL STORES | ||||||||||||||||||||||
170 | NA | Pharmaceutical Tender Awards | The opening of the 2023/2025 Pharmaceutical Tender Period | Jul-23 | Dec-23 | Quarterly | Open Tender | 10 | Tender | |||||||||||||
171 | NA | Non- Pharmaceutical Tender Awards | The opening of the 2023/2025 Non-Pharmaceutical Tender Period | Aug-23 | TBD | Quarterly | Open Tender | 10 | Tender | |||||||||||||
172 | NA | Board Room Video Conference and Recording implementation | To enhance sound recording in the training room for board meetings | Jan-24 | Mar-24 | 20 days | Request for Quotation | NA | Purchase Order | |||||||||||||
173 | NA | Server Infrastructure Upgrade at Head Office | To upgrade and refresh current server infrastructure or lift and shift physical and virtual servers to the cloud | Mar-24 | Apr-24 | 30 days | Request for Proposal | 10 | Purchase Order | |||||||||||||
174 | NA | 2 Core backup switches | Acquisition of two switches for backup and redundancy on the network | Mar-24 | Apr-24 | 30 days | Request for Quotation | NA | Purchase Order | |||||||||||||
175 | NA | 4 1500 VA UPS | UPS to support power backup to network devices | Jan-24 | Jan-24 | 20 days | Request for Quotation | NA | Purchase Order | |||||||||||||
176 | NA | Entainment & Refreshment | Coporate Catering | NA | NA | NA | NA | Request for Quotation | NA | Purchase Order | ||||||||||||
177 | NA | Medical Expenses | Staff Psychological Services - Employee Assistance Programme Staff/Executive Medicals | NA | NA | NA | NA | Request for Quotation | NA | Purchase Order | ||||||||||||
178 | NA | Office Supplies | Stationery and Office Supplies | NA | NA | NA | NA | Request for Quotation | NA | Purchase Order | ||||||||||||
179 | NA | Professional Fees | Annual Membership | NA | NA | NA | NA | Request for Quotation | NA | Purchase Order | ||||||||||||
180 | NA | Recruitment and Selection | Employee Background Checks/ Recruitment/Advertising | NA | NA | NA | NA | Request for Quotation | NA | Purchase Order | ||||||||||||
181 | NA | Staff Welfare | Medical Services | NA | NA | NA | NA | Request for Quotation | NA | Purchase Order | ||||||||||||
182 | NA | Training and Development | Training | NA | NA | NA | NA | Request for Quotation | NA | Purchase Order | ||||||||||||
183 | NA | Uniforms | Uniforms for Office Staff | NA | NA | NA | NA | Request for Quotation | NA | Purchase Order | ||||||||||||
184 | NA | Subscriptions HRPlus | HRIS (Human Resource Information System) | NA | NA | NA | NA | Request for Quotation | NA | Purchase Order | ||||||||||||
185 | 13/07/2023 | Outfitting Of Dormitories at Camp La Romain for The Relocation of Two (2) Companies of the 2nd Infantry Battalion of the Trinidad and Tobago Defence Force for the Ministry of National Security | Supply, delivery and installation of fixed and fixed furniture, fixtures & equipment | Aug-23 | Sep-23 | 3 months | Selective | 10 | Fixed Price | |||||||||||||
186 | Provision of MEP Construction Services for the Refurbishment of the NIB House and Family Court for the NIBTT | MEP Upgrade Works inclusive of HVAC, Elevator, Electrical, Plumbing | Nov-22 | Feb-23 | 10 months | Selective | 10 | Fixed Price | ||||||||||||||
187 | Modified Design Build Services for the Construction of the New Arima Licensing Office | Design and Construction of a single storey reinforced concrete building inclusive of outfitting | Jan-24 | Feb-24 | 10 months | Open Public | 10 | Fixed Price | ||||||||||||||
188 | Provision of Design Engineering Services for the Replacement of the Crawler Lifts at NALIS Building | Structural Condition Assessment and procurement, installation and commissioning of 2 No. crawler Lifts at NALIS Building | Dec-23 | Jan-24 | 3 months | Open Public | 10 | Fixed Price | ||||||||||||||
189 | Supply, Installation and Commissioning of AC Units at the CCLCS Valsayn Campus | Decommissioning of existing 5Ton Units and replacement with new units inclusive of ducting connections | Jan-24 | Feb-24 | 6 months | Selective | 10 | Fixed Price | ||||||||||||||
190 | Supply, Installation and Commissioning of Fire Watre & Potable Water Pumps at CCLCS Valsayn Campus | Installation of new fire water & potable water pumps inclusive of upgrade to water storage inclusive of plumbing | Jan-24 | Feb-24 | 6 months | Selective | 10 | Fixed Price | ||||||||||||||
191 | Supply, Installation of New Cooling Tower for Chill Water System at NALIS Building | Design and Installation of cooling tiwer and dismantling and disposal of existing | Jan-24 | Jun-24 | 6 months | Selective | 10 | Fixed Price | ||||||||||||||
192 | Design & Construction of New Meteorological Services Building | Design and construction of a new building to house the Meteorological Services Division (Trinidad) at the North Aviation Business Park at Piarco. | Dec-23 | Jan-25 | 11 months | Selective | 10 | Fixed Price | ||||||||||||||
193 | Development of Preliminary Designs and Project Budget for a Sewerage Treatment Plnat at Prisons Training College | 81103406 | Preparation of Preliminary designs and budgets for a new STP at the Prison Training College | Dec-23 | May-24 | 2.5 months | Selective | 10 | Fixed Price | |||||||||||||
194 | NWSTP 01/2023 | DB Services for the Santa Cruz WTP | 30000000 | Design Build Services for a Package WTP at the WASA Santa Cruz Area Office | Oct-23 | Dec-23 | 18 months | Open Public | 10 | Fixed Price | ||||||||||||
195 | NWSTP 02/2023 | DB Services for the Goldsboroughz WTP | 30000000 | Design Build Services for a Package WTP at Goldsborough Tobago | Oct-23 | Dec-23 | 18 months | Open Public | 10 | Fixed Price | ||||||||||||
196 | NWSTP 03/2023 | DB Services for the refurbishment of Chatham WTP | 30000000 | Design Build Services for the refurbishment of the existing WASA WTP at Chatham | Dec-23 | Feb-24 | 18 months | Open Public | 10 | Fixed Price | ||||||||||||
197 | NWSTP 04/2023 | DB Services for the refurbishment of Freeport WTP | 30000000 | Design Build Services for the refurbishment of the existing WASA WTP at Freeport | Dec-23 | Feb-24 | 18 months | Open Public | 10 | Fixed Price | ||||||||||||
198 | NWSTP 05/2023 | DB Services for the refurbishment of Guanapo WTP | 30000000 | Design Build Services for the refurbishment of the existing WASA WTP at Guanapo | Dec-23 | Feb-24 | 18 months | Open Public | 10 | Fixed Price | ||||||||||||
199 | NWSTP 06/2023 | DB Services for the refurbishment of Navet WTP | 30000000 | Design Build Services for the refurbishment of the existing WASA WTP at Navet | Dec-23 | Feb-24 | 18 months | Open Public | 10 | Fixed Price | ||||||||||||
200 | NWSTP 07/2023 | DB Services for the refurbishment of North Oropouche WTP | 30000000 | Design Build Services for the refurbishment of the existing WASA WTP at North Oropouche | Dec-23 | Feb-24 | 18 months | Open Public | 10 | Fixed Price | ||||||||||||
201 | WSSP 01/2023 | Expression of Interest | 30000000 | Expression of Interst for the Design Build Finance of Several Package Reverse Osmosis and Conventional WTP's in Trinidad | Nov-23 | Dec-23 | NA | Pre-qualified | 10 | NA | ||||||||||||
202 | WSSP 02/2023 | DBF Services for a Package Desal plant in Icacos | 30000000 | DBF Services for a Package Desal plant in Icacos | Jan-24 | Feb-24 | 18 months |